Saturday, January 21, 2012

AUP College of Medicine - Plan C [B-1+B-2]


Plan A [marked with + sign]: 8,933 sq.m. for PhP150 mil [PhP 16,791.67 per sq.m]



http://wikimapia.org/#lat=14.223985&lon=121.0416931&z=15&l=0&m=b&search=adventist%20university%20of%20the%20philippines




 Plan C: 4,733 sq.m. for USD1.9mil [USD401.44 per sq.m.]

The total cost of the building project is USD $1.9 Million, with a total area of 4,733 sq.m.

To date [as of 15 January 2012], we received USD $216,000.00 cash and  $ 888,443.00 pledges.

We are still short of about USD $ .9 Million to complete the building project budget and to finish the building construction as planned, so we can offer the course Doctor of Medicine on June, 2013.

Lilibeth de Belen-Casel
Director, Alumni Affairs and Philanthropy Office
Adventist University of the Philippines

























Comparative Charts of Plans A, B, C
Total Floor Areas in Square Meters
Approx. Construction Costs Per Square Meter in US$


https://docs.google.com/spreadsheet/pub?hl=en_US&hl=en_US&key=0AnxFdTu7W9TldFpqMHhySXBzNE9IQjNZbG5OeXJieGc&output=html

Plan A: 8,933 sq.m. for PhP150 mil [PhP 16,791.67 per sq.m] @Php40 to one US$ = US$420

Plan B-1: 1,532 sq.m. for PhP70 mil. [PhP 45,691.00 per sq.m.] consists of several rooms at USD 1,659,573.00 [roughly USD 1,083.27 per sq.m.]


Plan C [B-1 + B-2]: 4,733 sq.m. for USD1.9mil [USD401.44 per sq.m.]  Note the extensions in the back. There are now two facades: the original Plan B Front North Western View and the Plan C South Eastern View extensions/additions in the back. Briefly, it was a leap from a two-storey Plan B: 1,532 sq.m. to a three-storey Plan C: 4,733 sq.m. with a covered car park in the basement and additional rooms.
https://docs.google.com/spreadsheet/ccc?key=0AnxFdTu7W9TldC00TXBlQTlJV1ZrQk5lRWg4djM0cXc&hl=en_US#gid=0